Contract No: HK/2011/07 Wanchai
Development Phase II and Sampling, Field Measurement and Testing Work (Stage 2) Environmental Permit
no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009,
FEP-03/364/2009, FEP-05/364/2009/A,
FEp-06/364/2009/a, FEP-07/364/2009/A and FEP-08/364/2009/A Monthly
Environmental Monitoring & Audit Report
- august 2012 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
11 September 2012 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status of Environmental Licensing and Permitting under the
Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring.
6.4 Review of the Reasons for and the Implications of
Non-compliance
6.5 Summary of action taken in the event of and follow-up on
non-compliance
7. Cumulative Construction Impact
due to the Concurrent Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under this Project
Table
2.2 Details of Individual Contracts under the Project
Table
2.3 Contact Details of Key Personnel
Table
3.2 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/17
Table
3.3 Summary of submission status under FEP-03/364/2009
Table
3.4 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/01
Table
3.5 Summary of submission status under FEP-02/364/2009
Table
3.6 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/02
Table
3.7 Summary of submission status under FEP-01/364/2009
Table
3.8 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/18
Table
3.9 Summary of submission status under FEP-05/364/2009/A
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.11 Summary of submission status under FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Table 3.13 Summary of submission status under FEP-07/364/2009/A
Table 3.14 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Table
4.1 Noise Monitoring Stations
Table
4.2 Real Time Noise Monitoring Stations
Table
4.3 Air Monitoring Stations
Table
5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Table
5.2 Noise Monitoring Stations for Contract no. HY/2009/18
Table
5.3 Noise Monitoring Station for Contract no HK/2009/01 and
HK/2009/02
Table
5.4 Noise Monitoring Stations for Contract no. HY/2009/15
Table
5.5 Noise Monitoring Stations for Contract no. HY/2009/19
Table
5.6 Real Time Noise Monitoring Stations for Contract no.
HY/2009/17
Table
5.7 Real Time Noise Monitoring Stations for Contract no.
HY/2009/19
Table
5.8 Air Monitoring Station for Contract no. HY/2009/17
Table
5.9 Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10 Air Monitoring Station for Contract no. HK/2009/01
Table 5.11 Air Monitoring Station for Contract no. HK/2009/02
Table 5.12 Air Monitoring Station for Contract no. HY/2009/15
Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table 5.14 Details of Waste Disposal for Contract no. HY/2009/17
Table 5.15 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/02
Table
5.17 Details of Waste Disposal for Contract no. HY/2009/18
Table
5.18 Details of Waste Disposal for Contract no. HY/2009/15
Table
5.19 Details of Waste Disposal for Contract no. HY/2009/19
Table
5.20 Details of Waste Disposal for Contract no. HK/2010/06
Table
8.1 Summary of Environmental Inspections for Contract no.
HY/2009/15
Table
8.2 Summary of Environmental Inspections for Contract no. HY/2009/18
Table
8.3 Summary of Environmental Inspections for Contract no.
HY/2009/19
Table
8.4 Summary of Environmental Inspections for Contract no.
HK/2009/01
Table
8.5 Summary of Environmental Inspections for Contract no.
HK/2009/02
Table
8.6 Summary of Environmental Inspections for Contract no.
HK/2010/06
Table
9.1 Cumulative Statistics on Complaints
Table
9.2 Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and Graphical Presentations
Appendix
5.3 Air Quality Monitoring Results and
Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works under FEP-03/364/2009
¡P
ELS
works for basement construction for pile cap construction.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
¡P
Excavation
of trial pit
¡P
Transplanting
of trees
¡P
Hoarding
erection and modification
¡P
Installation
of couplers, UU detection, trial trench, pre-drilling
¡P
Site
investigation and pre-drill works
¡P
Excavation
¡P
Diaphragm
wall construction
¡P
Sheet
Piling
¡P
Drainage
works
¡P
Tunnel
works
¡P
Top
down slab construction
¡P
Trough
structure construction and associated drilling and grouting
¡P
Road
works
¡P
OHVD
installation
¡P
Site
access set up at Portion 6
¡P
TTA
near Gate 3
¡P
Pumping
test
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre - Tunnel Works under FEP-02/364/2009
¡P
Diaphragm
wall construction works for CWB (Stage2) at the northern side
¡P
Pre-drilling
works for CWB (Stage 2)
¡P
Construction
of exhaust duct structure (Bay 1 and Bay 2) including waterproofing and protective
screeding
¡P
Trimming
of SCL Diaphragm wall head
¡P
Construction
of SCL top slab (Bay 2 & Bay 3)
¡P
Remedial
works for SCL Diaphragm Wall
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Deep
excavation works reached -19mPD to -18mPD on the eastern and western portion of
the site respectively
¡P
Pre-drill
holes
¡P
Guide
wall construction for Eastern Bulkhead Diaphragm wall at tunnel portion 3 &
4 area
¡P
Silo
tank, desander and bar bending yard setup for diaphragm wall construction at
existing helipad
¡P
Diaphragm
wall construction of panel P110
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Diaphragm
wall construction works at TS4
¡P
Rock
breaking works at TPCWAE
¡P
Removal
of temporary reclamation at TS1
¡P
Dismantling
of scaffold in tunnel box at TS1
¡P
Preparation
works for bored piling at eastern breakwater
¡P
Mined
tunnel preparation works at TPCWAE
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road
works at Watson Road
¡P
Bored
piling (Land)
¡P
Ground
contamination assessment
¡P
Pre-drilling
works for bored pile and Diaphragm wall
¡P
D-wall
Construction (North & South Section)
¡P
Guide
wall construction for D-wall / Barette at North side
¡P
Construction
works for Box Culvert T
¡P
Marine
Piling
¡P
Construct
ion of socket-H pile
¡P
Construction
of pre-bored H-pile works for Culvert U
¡P
Construction
of 1500f drainage pipe
¡P
Construction
of Pile cap & column (Land)
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P
Construction
of Pre-cast Unit in China
Noise Monitoring
Air Monitoring
CMA1b: from 27 Jul and 20 August 2012 to 31 Jul and
21 August 2012
CMA2a: from 27 Jul and 8 August 2012 to 28 Jul and 10
August 2012
CMA5a: from 20 August 2012 to 21 August 2012
MA1w: from 27 Jul 2012 to 28 Jul 2012
CMA2a: 9 August 2012 to 11 August 2012
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Contract no.
HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works under FEP-03/364/2009
¡P
ELS
works for basement construction for pile cap construction.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Excavation
of trial pit
¡P
Transplanting
of trees
¡P
Hoarding
erection and modification
¡P
Installation
of couplers, UU detection, trial trench, pre-drilling
¡P
Site
investigation and pre-drill works
¡P
Excavation
¡P
Diaphragm
wall construction
¡P
Sheet
Piling
¡P
Drainage
works
¡P
Tunnel
works
¡P
Top
down slab construction
¡P
Trough
structure construction and associated drilling and grouting
¡P
Road
works
¡P
OHVD
installation
¡P
Pipe-piling
works
¡P
Cooling
main bridge construction
¡P
Bridge
A construction
¡P
Pre-bored
H-pile
¡P
Pumping
test
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Preparation
works for pre-bored H-pile installation including excavation to +2mPD at
northern side between Ch120 and Ch190
¡P
Backfilling
for the extent of exhaust duct section for pipe laying works for cross harbour
watermains
¡P
Construction
of SCL top slab (Bay 1 and Bay 2)
¡P
Remedial
works for SCL Diaphragm Wall
¡P
Installation
of dewatering system and equipment at SCL
¡P
Backfilling
works of the Area 3 to the required level for subsequent handover of site area
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Deep
excavation and strut installation works below -18mPD for western tunnel portion
and below -19mPD for eastern tunnel portion
¡P
Diaphragm
wall construction for Panel C107, P108, C109, C111, P112, C113, P114 and C115
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Diaphragm
wall construction works at TS4
¡P
ELS
preparation works at TS4
¡P
Rock
breaking works at TPCWAE
¡P
Tunnel
works at TS1
¡P
Bored
piling at eastern breakwater
¡P
Horizontal
drilling along west portal of mined tunnel
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road
works at Watson Road
¡P
Bored
piling (Land)
¡P
Ground
contamination assessment
¡P
Pre-drilling
works for bored pile and Diaphragm wall
¡P
D-wall
Construction (North & South Section)
¡P
Guide
wall construction for D-wall / Barette at North side
¡P
Construction
works for Box Culvert T
¡P
Marine
Piling
¡P
Construct
ion of socket-H pile
¡P
Construction
of pre-bored H-pile works for Culvert U
¡P
Construction
of 1500f drainage pipe
¡P
Construction
of Pile cap & column (Land)
¡P
Dismantling
of marine platform
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P
Construction
of Pre-cast Unit in China
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos.
FEP-01/364/2009,
FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and FEP-08/364/2009/A to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A,
Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009,
FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and
FEP-08/364/2009/A during the period July to Aug 2012. The cut-off date of reporting is at 27th of each reporting
month.
Section 1 Introduction ¡V details the
scope and structure of the report.
Section 2 Project
Background ¡V summarizes background and scope of the project, site
description, project organization and contact details of key personnel during
the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the
status of valid Environmental Permits / Licenses during the reporting period.
Section 4 Monitoring
Requirements ¡V summarizes all monitoring parameters, monitoring
methodology and equipment, monitoring locations, monitoring frequency, criteria
and respective event and action plan and monitoring programmes.
Section 5 Monitoring
Results ¡V summarizes the monitoring results obtained in the
reporting period.
Section 6 Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances
environmental parameters.
Section 7 Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the
concurrent activities of the concurrent Projects.
Section 8 Site Inspection ¡V summarizes the findings of weekly site
inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and
prosecution
Section 10 Conclusion
2.1.1.
¡§Wan
Chai Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai
Bypass and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are
Designated
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key
purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai
North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested east-west Connaught Road Central/Harcourt Road / Gloucester Road
Corridor (the Corridor) which is currently operating beyond its capacity. The
CWB will provide relief to the existing congestion along the Corridor and cater
for the anticipated growth of traffic on Hong Kong Island. Without the CWB and
its access roads, there will not be sufficient capacity to serve the heavy
traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure
2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and
Island Eastern Corridor Link (IECL) includes:
¡P
A
dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
¡P
Tunnel
control buildings and ventilation buildings;
¡P
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
Causeway Bay area;
¡P
Associated
road lighting, road signing, traffic control and surveillance system; and
¡P
Other
associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to
be granted by the DEP before they may be
either constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2
DPs.
Table 2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to
the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The
details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual
Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre ¡V Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
13 July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact
Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 8332 |
3529 2829 |
|
Lam Woo & CO.,
LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Site Agent |
Mr. Tony Au |
9725 5874 |
2566 7522 |
||
Sub Agent |
Mr. Johnny Wong |
9725 5870 |
2566 7522 |
||
Chun Wo ¡V Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
Mr. PL Yue |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub Agent |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 2467 |
|||
Construction
Manager |
Mr KK Yuen |
9498 1213 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental
Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
|
|
Environmental
Supervisor |
Mr. Yeung Sze King |
9047 9952 |
|
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Calvin Leung |
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
|
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Engineer Graduate |
Phil Mak |
2214 7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
K. W. Lee |
6461 4623 |
|||
|
|
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|
|
|
Environmental Supervisor |
Bosco Lee |
2214 7711 |
|
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. P.J. Fan |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. David Lau |
3557 6358 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Environmental Supervisor |
Mr. Kelven Yip |
3557 6347 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
Mr. Clement
Pang |
9735 9200 |
|||
ENVIRON Hong Kong Limited |
Independent Environmental
Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no.
HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works under FEP-03/364/2009
¡P
ELS
works for basement construction for pile cap construction.
Contract
no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under
FEP-05/364/2009/A
¡P
Excavation
of trial pit
¡P
Transplanting
of trees
¡P
Hoarding
erection and modification
¡P
Installation
of couplers, UU detection, trial trench, pre-drilling
¡P
Site
investigation and pre-drill works
¡P
Excavation
¡P
Diaphragm
wall construction
¡P
Sheet
Piling
¡P
Drainage
works
¡P
Tunnel
works
¡P
Top
down slab construction
¡P
Trough
structure construction and associated drilling and grouting
¡P
Road
works
¡P
OHVD
installation
¡P
Site
access set up at Portion 6
¡P
TTA
near Gate 3
¡P
Pumping
test
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Diaphragm
wall construction works for CWB (Stage2) at the northern side
¡P
Pre-drilling
works for CWB (Stage 2)
¡P
Construction
of exhaust duct structure (Bay 1 and Bay 2) including waterproofing and protective
screeding
¡P
Trimming
of SCL Diaphragm wall head
¡P
Construction
of SCL top slab (Bay 2 & Bay 3)
¡P
Remedial
works for SCL Diaphragm Wall
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Deep
excavation works reached -19mPD to -18mPD on the eastern and western portion of
the site respectively
¡P
Pre-drill
holes
¡P
Guide
wall construction for Eastern Bulkhead Diaphragm wall at tunnel portion 3 &
4 area
¡P
Silo
tank, desander and bar bending yard setup for diaphragm wall construction at
existing helipad
¡P
Diaphragm
wall construction of panel P110
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
¡P
Diaphragm
wall construction works at TS4
¡P
Rock
breaking works at TPCWAE
¡P
Removal
of temporary reclamation at TS1
¡P
Dismantling
of scaffold in tunnel box at TS1
¡P
Preparation
works for bored piling at eastern breakwater
¡P
Mined
tunnel preparation works at TPCWAE
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
¡P
Road
works at Watson Road
¡P
Bored
piling (Land)
¡P
Ground
contamination assessment
¡P
Pre-drilling
works for bored pile and Diaphragm wall
¡P
D-wall
Construction (North & South Section)
¡P
Guide
wall construction for D-wall / Barette at North side
¡P
Construction
works for Box Culvert T
¡P
Marine
Piling
¡P
Construct
ion of socket-H pile
¡P
Construction
of pre-bored H-pile works for Culvert U
¡P
Construction
of 1500f
drainage pipe
¡P
Construction
of Pile cap & column (Land)
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
¡P
Construction
of Pre-cast Unit in China
2.4.4.
In
coming reporting month, the principal work activities of individual contracts
are anticipated as follows:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD
Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009
¡P
ELS
works for basement construction for pile cap construction.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Excavation
of trial pit
¡P
Transplanting
of trees
¡P
Hoarding
erection and modification
¡P
Installation
of couplers, UU detection, trial trench, pre-drilling
¡P
Site
investigation and pre-drill works
¡P
Excavation
¡P
Diaphragm
wall construction
¡P
Sheet
Piling
¡P
Drainage
works
¡P
Tunnel
works
¡P
Top
down slab construction
¡P
Trough
structure construction and associated drilling and grouting
¡P
Road
works
¡P
OHVD
installation
¡P
Pipe-piling
works
¡P
Cooling
main bridge construction
¡P
Bridge
A construction
¡P
Pre-bored
H-pile
¡P
Pumping
test
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Preparation
works for pre-bored H-pile installation including excavation to +2mPD at
northern side between Ch120 and Ch190
¡P
Backfilling
for the extent of exhaust duct section for pipe laying works for cross harbour
watermains
¡P
Construction
of SCL top slab (Bay 1 and Bay 2)
¡P
Remedial
works for SCL Diaphragm Wall
¡P
Installation
of dewatering system and equipment at SCL
¡P
Backfilling
works of the Area 3 to the required level for subsequent handover of site area
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Deep
excavation and strut installation works below -18mPD for western tunnel portion
and below -19mPD for eastern tunnel portion
¡P
Diaphragm
wall construction for Panel C107, P108, C109, C111, P112, C113, P114 and C115
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Diaphragm
wall construction works at TS4
¡P
ELS
preparation works at TS4
¡P
Rock
breaking works at TPCWAE
¡P
Tunnel
works at TS1
¡P
Bored
piling at eastern breakwater
¡P
Horizontal
drilling along west portal of mined tunnel
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road
works at Watson Road
¡P
Bored
piling (Land)
¡P
Ground
contamination assessment
¡P
Pre-drilling
works for bored pile and Diaphragm wall
¡P
D-wall
Construction (North & South Section)
¡P
Guide
wall construction for D-wall / Barette at North side
¡P
Construction
works for Box Culvert T
¡P
Marine
Piling
¡P
Construct
ion of socket-H pile
¡P
Construction
of pre-bored H-pile works for Culvert U
¡P
Construction
of 1500f drainage pipe
¡P
Construction
of Pile cap & column (Land)
¡P
Dismantling
of marine platform
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P
Construction
of Pre-cast Unit in China
3.1.1.
A
summary of the current status on licences and/or permits on environmental
protection pertinent to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Valid |
3.1.2.
Due to
the multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass
(CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009
3.1.3.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission
under FEP-03/364/2009 for
contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 ¡V 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July 2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3 Summary
of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management
Organization of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and
2.8 |
Submission of works
schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management
Plan |
1 September 2010 |
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4.
The construction works was
completed, and the FEP was surrendered by the Contractor on 11 February 2011.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre ¡V Tunnel Works under FEP-02/364/2009
3.1.5.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission
under FEP-02/364/2009 for
contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling
equipment |
GW-RS0158-12 |
24 Feb 2012 |
24 Feb 2012 to 23 Aug 2012 |
Valid (Expired on 23 Aug
2012) |
|
GW-RS0181-12 |
24 Feb 2012 |
27 Feb 2012 to 23 Aug 2012 |
Valid (Expired on 23 Aug
2012) |
|
GW-RS0213-12 |
28 Feb 2012 |
29 Feb 2012 to 27 Aug 2012 |
Valid (Expired on 27 Aug
2012) |
|
GW-RS0225-12 |
02 Mar 2012 |
14 Mar 2011 to
13 Sep 2012 |
Valid |
|
GW-RS0227-12 |
02 Mar 2012 |
16 Mar 2011 to 15 Sep 2012 |
Valid |
|
GW-RE0174-12 |
05 Mar 2012 |
30 Mar 2012 to 29 Sep 2012 |
Valid |
|
GW-RS0312-12 |
28 Mar 2012 |
30 Mar 2012 to 29 Sep 2012 |
Valid |
|
GW-RS0314-12 |
29 Mar 2012 |
30 Mar 2012 to 25
Sep 2012 |
Cancelled |
|
GW-RS0356-12 |
03 Apr 2012 |
11 Apr 2012 to 29 Sep 2012 |
Valid |
|
GW-RS0394-12 |
16 Apr 2012 |
19 Apr 2012 to 12 Oct 2012 |
Valid |
|
GW-RS0459-12 |
3 May 2012 |
7 May 2012 to 6 Nov 2012 |
Cancelled |
|
GW-RS0460-12 |
10 May 2012 |
13 May 2012 to 6
Nov 2012 |
Valid |
|
GW-RS0514-12 |
14 May 2012 |
27 May 2012 to 26
Nov 2012 |
Valid |
|
GW-RS0545-12 |
24 May 2012 |
26 May 2012 to 25
Nov 2012 |
Valid |
|
GW-RS0546-12 |
25 May 2012 |
26 May 2012 to 25
Nov 2012 |
Valid |
|
GW-RS0731-12 |
5 Jul 2012 |
05 Jul 2012 to 01 Jan 2013 |
Cancelled |
|
GW-RS0760-12 |
18 Jul 2012 |
20 Jul 2012 to 19 Jan 2013 |
Valid |
|
GW-RS0771-12 |
23 Jul 2012 |
23 Jul 2012 to 31 Aug 2012 |
Valid |
|
GW-RS0806-12 |
3 Aug 2012 |
4 Aug 2012 to 3 Feb
2012 |
Valid |
|
GW-RS0823-12 |
3 Aug 2012 |
3 Aug 2012 to 2 Feb 2012 |
Valid |
|
GW-RS0852-12 |
16 Aug 2012 |
16 Aug 2012 to 1 Feb
2012 |
Valid |
|
GW-RS0855-12 |
16 Aug 2012 |
17 Aug 2012 to 9 Feb 2012 |
Valid |
|
GW-RS0862-12 |
20 Aug 2012 |
28 Aug 2012 to 27 Feb
2012 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00009641-2011 |
24 Jul
2011 |
31 Jul
2016 |
Valid |
Billing account
under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.5 Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
3.1.6.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission
under FEP-01/364/2009 for
contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0037-12 |
19 Jan 2012 |
1 Feb 2012 to 31 July 2012 |
Valid (Expired on 31 July 2012) |
|
GW-RS0051-12 |
19 Jan 2012 |
1 Feb 2012 to 31 July 2012 |
Valid (Expired on 31 July 2012) |
|
GW-RS0086-12 |
30 Jan 2012 |
3 Feb 2012 to 2 Aug 2012 |
Cancelled |
|
GW-RS0105-12 |
3 Feb 2012 |
10 Feb 2012 to 9 Aug 2012 |
Cancelled |
|
GW-RS0153-12 |
17 Feb 2012 |
21 Feb 2012 to 20 Aug 2012 |
Cancelled |
|
GW-RS0233-12 |
6 Mar 2012 |
9 Mar 2012 to 8 Sept 2012 |
Cancelled |
|
GW-RS0255-12 |
14 Mar 2012 |
17 Mar 2012 to 15 Sept 2012 |
Valid |
|
GW-RE0283-12 |
5 Apr 2012 |
1 May 2012 to 30 Nov 2012 |
Valid |
|
GW-RS0301-12 |
20 Mar 2012 |
21 Mar 2012 to 20 Sept 2012 |
Cancelled |
|
GW-RS0303-12 |
26 Mar 2012 |
27 Mar 2012 to 27 Sept 2012 |
Valid |
|
GW-RS0341-12 |
3 Apr 2012 |
28 Apr 2012 to 27 Oct 2012 |
Valid |
|
GW-RS0348-12 |
3 Apr 2012 |
10 Apr 2012 to 9 Oct 2012 |
Valid |
|
GW-RS0380-12 |
12 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Valid |
|
GW-RS0388-12 |
13 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Valid |
|
GW-RS0418-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Valid |
|
GW-RS0420-12 |
30 Apr 2012 |
18 May 2012 to 17 Nov 2012 |
Cancelled |
|
GW-RS0423-12 |
30 Apr 2012 |
19 May 2012 to 18 Nov 2012 |
Cancelled |
|
GW-RS0427-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Valid |
|
GW-RS0445-12 |
30 Apr 2012 |
1 May 2012 to 25 Sept 2012 |
Valid |
|
GW-RS0467-12 |
10 May 2012 |
14 May 2012 to 10 Nov 2012 |
Cancelled |
|
GW-RS0533-12 |
21 May 2012 |
21 May 2012 to 10 Nov 2012 |
Valid |
|
GW-RS0550-12 |
25 May 2012 |
7 June 2012 to 6 Dec 2012 |
Valid |
|
GW-RS0611-12 |
14 June 2012 |
15 Jun 2012 to 28 Nov 2012 |
Valid |
|
GW-RS0633-12 |
13 June 2012 |
16 Jun 2012 to 14 Dec 2012 |
Valid |
|
GW-RS0671-12 |
25 June 2012 |
17 Jul 2012 to 16 Jan 2013 |
Valid |
|
GW-RS0730-12 |
9 July 2012 |
10 Jul 2012 to 8 Jan 2013 |
Valid |
|
GW-RS0736-12 |
9 July 2012 |
9 Jul 2012 to 8 Jan
2013 |
Valid |
|
GW-RS0739-12 |
9 July 2012 |
1 Aug 2012 to 31 Jan 2013 |
Valid |
|
GW-RS0814-12 |
3 Aug 2012 |
6 Aug 2012 to 5 Dec 2012 |
Valid |
|
GW-RS0850-12 |
10 Aug 2012 |
14 Aug 2012 to 13 Feb 2013 |
Valid |
|
GW-RS0870-12 |
21 Aug 2012 |
16 Sept 2012 to 31 Dec 2012 |
Valid |
Construction Noise
Permit (CNP) for piling equipment |
PP-RS0007-12 |
27 Mar 2012 |
28 Mar 2012 to 27 Sept 2012 |
Cancelled |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
Billing Account
under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as
Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as
Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table 3.7 Summary
of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
21 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan (Revision A) |
13 Jan 2012 |
Condition 2.11 |
Landscape Plan
(Revision B) |
21 Feb 2012 |
Condition 2.9 |
Noise Management Plan
(Rev.A) |
13 Jan 2012 |
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
3.1.7.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.8 and Table 3.9.
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP) for non-piling
equipment |
GW-RS0261-12 |
09 Mar 2012 |
10 Mar 2012 ¡V |
Cancelled |
|
GW-RS0769-12 |
23 Jul 2012 |
25 Jul 2012 ¡V |
Valid |
|
GW-RS0833-12 |
09 Aug 2012 |
25 Jul 2012 ¡V |
Valid |
Discharge Licence |
WT00012998-2012 |
25 May 2012 |
31 Jan 2016 |
Valid |
Registration as a Waste Producer |
WPN:
8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Registration
completed |
Billing Account
under Waste Disposal Ordinance (Land) |
Account No.:
7011587 |
11 Oct 2010 |
Account approved |
Valid |
Table 3.9 Summary
of submission status under FEP-05/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management
Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan
(Rev. 5) |
12 March 2012 |
Contract
no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
3.1.8.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for
contract no. HY/2009/15 are shown in Table 3.10 and Table 3.11
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling
equipment |
GW-RS0150-12 |
22 Feb 2012 |
27 Feb 2012 to 24 Aug 2012 |
Cancelled |
|
GW-RS0094-12 |
1 Feb 2012 |
3 Feb 2012 to 31 Jul 2012 |
Valid (Expired on 31 Jul
2012) |
|
GW-RS0330-12 |
29 Mar 2012 |
3 Apr 2012
to 21 Sep 2012 |
Cancelled |
|
GW-RS0328-12 |
30 Mar
2012 |
1 Apr
2012 to 22 Sep
2012 |
Valid |
|
GW-RS0190-12 |
28 Feb
2012 |
28 Feb
2012 to 11 Aug
2012 |
Cancelled |
|
GW-RS0249-12 |
10 Feb 2012 |
9 Mar 2012 to 31 Aug 2012 |
Valid |
|
GW-RS0552-12 |
24 May 2012 |
25 May 2012 to 20 Oct 2012 |
Cancelled |
|
GW-RS0586-12 |
4 Jun
2012 |
5 Jun
2012 to 30 Sep
2012 |
Valid |
|
GW-RS0695-12 |
24 Jun
2011 |
25 Jun
2012 to 21 Dec
2012 |
Valid |
|
GW-RS0700-12 |
26 Jun
2012 |
26 Jun
2012 to 25 Dec
2012 |
Valid |
|
GW-RS0607-12 |
12 Jun
2012 |
13 Jun
2012 to 7 Dec
2012 |
Valid |
|
GW-RS0789-12 |
27 Jul
2012 |
1 Aug
2012 to 25 Jan
2013 |
Valid |
Registration as a Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010
to 27 Jan 2016 |
Valid |
Billing Account under Waste Disposal Ordinance
(Dumping by Vessel) |
7011761 |
10 Jul 2012 |
17 Jul 2012 to 16 Oct 2012 |
Valid |
Water Discharge License (Discharge at TS1) |
WT00008780-2011 |
24 Nov 2011 |
24 Nov 2011 to 31 Mar 2016 |
Valid |
Water Discharge License (Discharge at Hung Hing Road) |
WT00010482-2011 |
30 Sep 2011 |
30 Sep 2011 to 30 Sep 2013 |
Cancelled |
Water Discharge License (Discharge at CHT area) |
WT00012941-2012 |
10 May 2012 |
10 May 2012 to 31 May 2014 |
Valid |
Water Discharge License (Discharge at TPCWAE) |
WT00011322-2011 |
15 Dec 2011 |
15 Dec 2011 to 31 Dec 2013 |
Valid |
Water Discharge License (Discharge at TS4) |
WT00011718-2012 |
16 Jan 2012 |
16 Jan 2012 to 31 Jan 2014 |
Valid |
Table 3.11 Summary
of submission status under FEP-06/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition
2.6 |
Management
Organization of Main Construction Companies |
11 Mar 2011 |
Amendment
for Management Organization of Main Construction Companies |
16 May 2011 |
|
Condition
2.7 |
Works Schedule |
15 Mar
2011 |
Condition
2.8 |
Location
Plan |
15 Mar
2011 |
Condition
2.23 |
Noise
Management Plan |
6 May
2011 |
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
3.1.9.
The current status on licences and/or permits on
environmental protection pertinent and submission under
FEP-07/364/2009/A for
contract no. HY/2009/19 are shown in Table 3.12 and Table
3.13.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification of Works Under APCO |
326160 |
24 Jan
2011 |
N/A |
Valid |
Registration as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Application for Vessel Disposal |
7012306 |
21 July 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) |
GW-RS0180-12 |
22-Feb-12 (Effective 27-Feb-12) |
26-Aug-12 |
Valid (Expired on 26-Aug-12) |
|
GW-RS0507-12 |
22-May-12 (Effective 24-May-12) |
23-Nov-12 |
Cancelled |
|
GW-RS0589-12 |
18-Jun-12 |
17-Dec-12 |
Valid |
|
GW-RS0286-12 |
23-Mar-12 (Effective 27-Mar-12) |
26-Sep-12 |
Cancelled |
|
GW-RS0885-12 |
27-Aug-12 |
26-Feb-13 |
Valid |
Water Discharge Licence |
WT00010093-2011 |
31-Aug-11 |
30-Sep-16 |
Valid |
|
WT00010865-2011 |
3-Nov-11 |
30-Nov-16 |
Valid |
Table 3.13 Summary
of submission status under FEP-07/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition
2.9 |
Noise
Management Plan |
02 Jun 2011 |
Condition
2.13 |
Landscape
Plan |
16 March 2012 |
Condition 2.9 |
Noise Management Plan(Rev.2) |
28-Oct-11 |
3.1.10.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission
under FEP-08/364/2009/A for
contract no. HK/2010/06 showed in Table 3.14 and Table 3.15.
Table 3.14 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-08/364/2009/A |
15 June 2012 |
N/A |
Valid |
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
No submission has been made under FEP-08/364/2009/A in this reporting
month.
Noise Monitoring Stations
4.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1.
Appendix 4.1 shows the established Action/Limit Levels for the
monitoring works.
Table 4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church
Henrietta Secondary School |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
*M8 |
City Hall |
* Remark 1: Location ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
4.1.2.
Review of feasibility on the real time noise
monitoring stations was conducted in July with IEC. Station, RTN1a, Tung Lo Wan
fireboat Station was found not appropriate to be a monitoring station for
monitoring the IECL Piling works and Demolition after visited.
4.1.3.
The
noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the
monitoring works.
Table 4.2 Real Time Noise Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring
Parameters, Frequency and Duration
4.1.4.
The construction noise level shall be measured in terms of the
A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between 0700
and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary information for data auditing,
statistical results such as L10 and L90 shall also be
obtained for reference.
4.1.5.
Noise monitoring shall be carried out at all the
designated monitoring stations. The monitoring frequency shall depend on the
scale of the construction activities. The following is an initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
¡P
One
set of measurements between 0700 and 1900 hours on normal weekdays.
4.1.6.
Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 hours daily basis when
noise generating activities are underway:
¡P
One
set of measurements between 0700 and 1900 hours on normal weekdays.
¡P
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
¡P
One
set of measurements between 2300 and 0700 hours on next day on everyday.
4.1.7.
If construction works are extended to include works
during the hours of 1900 ¡V 0700 as well as public holidays and Sundays, additional
weekly impact monitoring shall be carried out during respective restricted
hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.8.
As referred to in the Technical Memorandum ™ issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.9.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
4.1.10.
The sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements will be accepted as valid only if the calibration level from
before and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring
Stations
4.2.1.
The air monitoring stations for the Project are
listed and shown in Table 4.3 and Figure 4.1.. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community Liaison
Centre |
North Point (Re-commenced on 14 November 2011) |
CMA2a |
Causeway Bay Community
Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Garden opposite to Pedestrian Plaza |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (western End of Podium) |
Central |
Remarks: As per
the ENPC meeting in March 2011, the monitoring stations CMA3a ¡V Future CWB site
office at Wanchai Waterfront Promenade was renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
4.2.3.
All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
¡P
0.6
¡V 1.7 m3 per minute adjustable flow range;
¡P
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
¡P
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
Capable
of providing a minimum exposed area of 406 cm2;
¡P
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
Equipped
with a shelter to protect the filter and sampler;
¡P
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
Equipped
with a flow recorder for continuous monitoring;
¡P
Provided
with a peaked roof inlet;
¡P
Incorporated
with a manometer;
¡P
Able
to hold and seal the filter paper to the sampler housing at horizontal position;
¡P
Easily
changeable filter; and
¡P
Capable
of operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement /
Analysis
4.2.7.
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8¡¨ x 10¡¨ shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10.
All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.2.11.
Current calibration certificates of equipments are
presented in Appendix
4.2.
5.0.1.
The environmental monitoring will be implemented
based on the division of works areas of each designated project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of
various contracts, latest status of work commencement and monitoring stations
is shown in Figure 2.1 and Figure 4.1. The monitoring results are
presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent contracts
are as follows:
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass
(CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass
(CWB) ¡V Central Interchange under FEP-05/364/2009/A
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section)
and Island Eastern Corridor Link under
FEP-07/364/2009
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central - Wan Chai Bypass at Wan Chai East
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central - Wan Chai Bypass over MTR Tsuen Wan Line
5.0.3.
The environment monitoring schedules for reporting
month and coming month are presented in Appendix 5.1.
5.1.1.
Monitoring for report of review baseline noise
level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20
June 2011, verified by IEC on 18 July 2011 and was approved by ER by January
2012. The new baseline is used for
the noise calculation of this reporting month starting from January 2012.
Contract no. HY/2009/17 ¡VCentral ¡V Wan
Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
5.1.2.
The proposed division of noise monitoring stations
for Contract no. HY/2009/17 are summarized in Table 5.1 below:
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
5.1.3.
No action or limit level exceedance was recorded
during daytime period in the reporting month. Noise monitoring results measured
in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.1.4.
Noise monitoring for the Central Interchange works
under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed
division of noise monitoring stations for Contract no. HY/2009/18 are
summarized in Table 5.2 below:
Table 5.2 Noise
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark : M7e has
become a reference station starting from 7 Aug 2012
5.1.5.
The
proposal of relocation of noise monitoring station M7e had been reviewed by EPD
on 3 Aug 2012, and agreed to establish a noise monitoring station (M8) at City
Hall, while M7e will be kept as a reference monitoring station.
5.1.6.
No action or limit level exceedance was recorded
during daytime period in the reporting month.
5.1.7.
Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009 and Contract no.
HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.8.
The commencement of construction works for Contract
no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under
FEP-01/364/2009 is on 26 April 2011. The proposed division of noise monitoring
stations are summarized in Table 5.3 below.
Table 5.3 Noise
Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.9.
No
action or limit level exceedance was recorded in the reporting month. Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
5.1.10. The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed divisions of
noise monitoring stations are summarized in Table 5.4 below.
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.11.
No action or limit level exceedance was recorded in
this reporting month.
5.1.12.
Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.1.13. Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division
of noise monitoring stations are summarized in Table 5.5 below.
Table 5.5 Noise
Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
5.1.14.
No action level exceedance was recorded in the
reporting month.
5.1.15.
One limit level exceedance was recorded on 24
August 2012 at M6 ¡V HK Baptist
Church Henrietta Secondary School in the reporting month.
5.1.16.
Major traffic jam and no major work activities were
observed during monitoring, the limit level exceedance was considered as
non-project related.
5.1.17.
Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2.
5.2.1.
FEHD
Hong Kong Transport Section
Whitefield Depot commenced
external wall renovation from 1 June 2012.
5.2.2.
No construction activity was conducted during
nighttime period (2300 to 0700) in this reporting month.
Contract no. HY/2009/17 ¡VCentral ¡V Wan
Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009 and Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
Table 5.6 Real Time Noise Monitoring Stations for Contract no. HY/2009/17
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitefield Depot |
Real time noise monitoring
results and graphical presentation during night time period are for information
only.
5.2.4.
No action and limit level exceedance were recorded
in the reporting period. Real time noise monitoring results measured in this reporting period are
reviewed and summarized. Details of real time noise monitoring results and
graphical presentation can be referred to Appendix 5.4 .
5.2.5.
The proposed division of noise monitoring stations
are summarized in Table 5.7 below. Real time noise monitoring for
major construction works under contract no. HY/2009/19 was commenced on 24
April 2011.
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitefield Depot |
RTN2 |
North Point |
Oil Street Community Liaison Center |
Real time noise monitoring results and graphical presentation during
night time period are for information only.
5.2.6.
Exceedances
were recorded at RTN2 ¡V Oil Street Community Liaison Center, between 0700 and
1900 hours throughout the reporting month.
Investigations found that the major noise impacts from 0700 and 1900
hours were arising from the demolition works near Oil Street Community
Liaison Center.
In addition, there was no noisy construction activity being conducted in
these periods. As such, the
exceedances were concluded as not project related.
5.2.7.
Real time noise monitoring results measured in this
reporting period are reviewed and summarized. Details of real time noise
monitoring results and graphical presentation can be referred to Appendix 5.4 . Details of the Notification of Exceedance can be
referred in Appendix 6.2.
5.3.1
Due to extension of site boundary by contractor of
HY/2009/19, location of air monitoring station CMA1b ¡V Oil Street Community
Liaison Centre has been finely adjusted on 21 April 2012.
5.3.2
Due to lack of electricity supply, the 24-hr TSP
monitoring at the following stations were rescheduled:
CMA1b: from 27 Jul and 20 August 2012 to 31 Jul and 21 August 2012
CMA2a: from 27 Jul and 8 August 2012 to 28 Jul and 10 August 2012
CMA5a: from 20 August 2012 to 21 August 2012
MA1w: from 27 Jul 2012 to 28 Jul 2012
5.3.3
Due to lack of electricity supply,
the 1-hr TSP monitoring at the following stations were rescheduled
CMA2a: 9 August 2012 to 11 August 2012
5.3.4
The data for the rescheduled air monitoring for
CMA1b, dated 30 April 2012, will be presented in the next monthly report (May
2012).
Contract no.
HY/2009/17 ¡VCentral ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works under FEP-03/364/2009
5.3.5
The proposed division of air monitoring stations
are summarized in Table 5.8 below. Air monitoring for the piling
works under contract no. HY/2009/17 was commenced on 8 October 2010.
Table 5.8 Air Monitoring Station for Contract no. HY/2009/17
Station |
Description |
CMA1b |
Oil Street
Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
5.3.6
Due
to electrical supply issues, the 24-hr and 1-hr TSP monitoring at CMA2a -
Causeway Bay Community Centre on 2 and 3 August 2012 were cancelled
respectively.
5.3.7
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/18 ¡V
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.3.8
Air monitoring for the Central Interchange works
under contract no. HY/2009/18 was commenced on 21 April 2011. The proposed
division of air monitoring stations are summarized in Table 5.9
below.
Table 5.9 Air Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
5.3.9
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre ¡V Tunnel Works under FEP-02/364/2009
5.3.10
The commencement of construction works for Contract
no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality monitoring
was commenced on 25 August 2011. The proposed division of air monitoring
stations are summarized in Table 5.10 below.
Table 5.10 Air Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
5.3.11
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.3.12
The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
air monitoring stations are summarized in Table 5.11 below.
Table 5.11 Air Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.13
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
5.3.14 The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Air quality monitoring was commenced on
14 July 2011. The proposed division of air monitoring
stations are summarized in Table 5.12 below.
Table 5.12 Air Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.15
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.3.16
The proposed division of air monitoring stations
are summarized in Table 5.13 below. Air monitoring for the tunnel
works under contract no. HY/2009/19 was commenced on 26 April 2011.
Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
5.3.17
Due
to electrical supply issues, the 24-hr and 1-hr TSP monitoring at CMA2a -
Causeway Bay Community Centre on 2 and 3 August 2012 was cancelled
respectively.
5.3.18
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no.
HY/2009/17 ¡VCentral ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works under FEP-03/364/2009
5.4.1.
No Inert and non-inert C&D wastes were disposed
in the reporting month. Details of the waste flow table are summarized in Table
5.14
Table 5.14 Details of Waste Disposal for Contract no. HY/2009/17
Waste Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
N/A |
||
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract nos. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre ¡V Tunnel Works under FEP-02/364/2009
5.4.2.
Inert and non-inert C&D wastes were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.15.
Table 5.15 Details
of Waste Disposal for Contract no. HK/2009/01
Waste Type |
|||
Inert C&D materials disposed |
22.035 |
19,347.225 |
TKO137, TM38 |
Inert C&D materials recycled |
355 |
3,057.96 |
N/A |
Non-inert C&D materials disposed |
57.10 |
901.40 |
SENT Landfill |
Non-inert C&D materials recycled |
483 |
147,583 |
N/A |
Chemical waste disposed |
450 |
7,300 |
N/A |
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
5.4.3.
Inert C&D & non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.16.
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/02
Inert C&D materials disposed |
1,345 |
174,298 |
TKO137, TM 38 |
Inert C&D materials recycled |
18,161 |
18,161 |
WCR2 |
Non-inert C&D materials disposed |
48 |
418 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed (kg) |
NIL |
4,721 |
N/A |
Remarks Contractor clarified and updated waste flow table for the
reporting month of April
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
5.4.4.
Inert C&D and non-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.17.
Table 5.17 Details of Waste Disposal for Contract
no. HY/2009/18
Inert C&D materials disposed |
9,417 |
48,084 |
T.K.O. 137, TM 38 |
Inert C&D materials recycled |
3,991 |
18,831 |
N/A |
Non-inert C&D materials disposed |
54 |
628 |
SENT Landfill |
Non-inert C&D materials recycled (tonnes) |
20.5 |
61.1 |
N/A |
Chemical waste disposed (kg) |
NIL |
2,985 |
N/A |
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
5.4.5.
Inert
& Non-inert C&D wastes were disposed of in this reporting month. Details of
the waste flow table are summarized in Table 5.18.
Table 5.18 Details of Waste Disposal for Contract
no. HY/2009/15
Inert C&D materials disposed |
15,892.8 |
162,003.4 |
Tuen Mun Area 38 |
|
7,040.9 |
149,811.2 |
TKO137 FB |
Inert C&D materials recycled |
NIL |
415.9 |
HY/2009/11 ex-PCWA TS4 |
Non-inert C&D materials disposed |
100.5 |
463.2 |
SENT Landfill |
Non-inert C&D materials recycled |
1.8 |
458.8 |
Xun Xiang Metalware Skylight Recycle (paper) |
Chemical waste disposed |
NIL |
11,036 |
Dunwell
Group |
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
5.4.6.
Inert and Non-inert C&D wastes were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.19.
Table 5.19 Details of Waste Disposal for Contract
no. HY/2009/19
Inert C&D
materials disposed |
17,610.48 |
149,268.92 |
N/A |
Inert C&D
materials recycled |
NIL |
1,801.91 |
N/A |
Non-inert C&D
materials disposed |
30.75 |
540.22 |
SENT Landfill |
Non-inert C&D
materials recycled |
NIL |
42.81 |
N/A |
Chemical waste
disposed |
NIL |
4.42 |
N/A |
Contract no. HK/2010/06 Wan
Chai Development Phase II - Central-Wan Chai Bypass over MTR Tsuen Wan Line
under FEP-08/364/2009/A
5.4.7.
No inert and Non-inert C&D wastes were disposed
of in this reporting month. Details of the waste flow table are summarized in Table
5.20.
Table 5.20 Details of Waste Disposal for Contract
no. HK/2010/06
Inert C&D materials disposed |
NIL |
NIL |
TM38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
Recyclers |
Chemical waste disposed |
NIL |
NIL |
N/A |
6.0.1.
The Event Action Plan for construction noise, air
qualities are presented in Appendix 6.1.
Contract no.
HY/2009/17 ¡VCentral ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works under FEP-03/364/2009
6.1.1.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
6.1.2.
No exceedance was recorded in the reporting month.
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II
¡V Central ¡V Wan Chai Bypass at Hong Kong Convention Exhibition Centre ¡V Tunnel
Works under FEP-02/364/2009
6.1.3.
No exceedance was recorded in the reporting month.
Contract
no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.4.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
6.1.5.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
6.1.6.
One limit level exceedance was recorded at M6 ¡V HK
Baptist Church Henrietta Secondary School on 24 August 2012 in the reporting
month.
Investigation found that major
traffic noise was contributed in the noise monitoring and not related to the Project.
Real Time Noise
Monitoring
Contract
no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V
Advanced piling works under FEP-03/364/2009
6.1.7.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.8.
Exceedances
were recorded at RTN2 ¡V Oil Street Community Liaison Centre, between 0700 and
1900 hours throughout the reporting month.
Investigations found that the major noise impacts from 0700 and 1900
hours were arising from the demolition works near Oil Street Community
Liaison Center.
In addition, there was no noisy construction activity being conducted in
these periods. As such, the
exceedances were concluded as not project related.
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD
Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009
6.2.1.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
6.2.2.
No exceedance was recorded in the reporting month.
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under
FEP-02/364/2009
6.2.3.
No exceedance was recorded in the reporting month.
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
6.2.4.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) FEP-06/364/2009/A
6.2.5.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.2.1
No exceedance was recorded in the reporting month.
6.3.1.
There was no non-compliance from the site audits in
the reporting period. The observations and recommendations made in each
individual site audit session were presented in Section 8.
6.3.2.
No project-related non-compliance from monitoring
was recorded in the reporting month.
7.0.1.
According to Condition 3.4 of the EP-364/2009/A,
this section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2.
According to the Monthly EM&A report (July
2012) of Central Reclamation Phase III (CRIII), filling works, road works, building
construction works and pipe works were performed in the August 2012 reporting
month. The water quality monitoring was completed in October 2011 and no
exceedance was recorded for air and noise monitoring. It can be concluded that cumulative
construction impact due to the concurrent activities of the current projects
with the Central Reclamation Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activity under Wan Chai Development Phase II
was marine works at HKCEC areas, cross-harbour Watermains, Fresh Watermains,
Cooling Watermains and Salt Watermains Installations, tunnel works at Wan Chai
East, diaphragm wall construction at TS4; dredging at TS2; temporary reclamation
removal at TS1 and deep excavation at TPCWAE TCBR1W.
Advanced piling works at FEHD Whitfield Depot, Central Interchange, and
diaphragm wall construction at North Point area. The major environmental impact
was water quality impact at Causeway Bay and Wan Chai. Land-based construction
activity were Diaphragm wall construction at TS4, deep excavation at TPCWAE
TCBR1W, piling works at FEHD Whitfield Depot, Diaphragm wall at Central and
North Point and tunnel works at Wan Chai East in the reporting month.
7.0.4.
The major environmental impacts generated from
advanced piling works at FEHD Whitfield Depot were undertaken and Diaphragm
wall construction at Central and tunnel works at Wan Chai East, IECL and
Causeway Bay typhoon shelter in the reporting month. No significant air impact
was anticipated in the reporting month. Besides, no Project-related exceedance was
recorded during the environmental monitoring events in the reporting
month. Thus, it is evaluated that
the cumulative construction impact from the concurrent projects including Wan
Chai Development Phase II was insignificant.
8.0.1.
During this reporting month, weekly environmental
site audits were conducted for Contracts no. HY/2009/15, HY/2009/17,
HY/2009/18, HY/2009/19, HK/2009/01, HK/2009/02 and HK/2010/06. No
non-conformance was identified during the site audits.
8.0.2.
Four site inspections for Contract no. HY/2009/15
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.1.
Table 8.1 Summary
of Environmental Inspections for Contract no. HY/2009/15
Date |
Item |
Observations |
Action taken by
Contractor |
Outcome |
31-Jul-12 |
120731_01 |
The oil was
observed on the water which should be removed and treated (TS1) |
Oil was
still observed on water. |
Follow up
on 7-Aug-12 |
7-Aug-12 |
120807_01 |
Better
maintenance of marine vessels to avoid oil leakage (TS1). |
Marine
vessels were maintained to avoid oil leakage. |
Completion
as observed on 14-Aug-12 |
7-Aug-12 |
120807_02 |
Better
maintenance of silt curtains to avoid holes and gaps (TS1). |
New silt
curtains were deployed |
Completion
as observed on 14-Aug-12 |
7-Aug-12 |
120807_03 |
Oil leakage
on ground should be removed (TS4). |
Oil leakage
was cleared as chemical waste. |
Completion
as observed on 14-Aug-12 |
7-Aug-12 |
120807_04 |
Haul roads
should be kept wet (TS4) |
Water
spraying on haul roads to keep the haul road wet. |
Completion
as observed on 14-Aug-12 |
7-Aug-12 |
120807_05 |
Muddy water
was observed to be running into public manhole, contractor should take
actions to prevent runoff. (Gate of TS4/ME4) |
Better
maintenance of wheel wash area to avoid runoff. |
Completion
as observed on 14-Aug-12 |
7-Aug-12 |
120807_06 |
Three side
cover of grouting machine should be maintained to ensure three sides and top
are covered (TPCWAE) |
The
grouting machine was no longer in use and three sides and top cover is
provided for the new grouting machine. |
Completion
as observed on 14-Aug-12 |
7-Aug-12 |
120807_07 |
Chemical
drums should be stored in appropriate
area (TPCWAE). |
Drip trays
were provided for chemical drums. |
Completion
as observed on 14-Aug-12 |
7-Aug-12 |
120807_08 |
Floating
refuse should be collected more regularly |
Floating
refuse at TS1 and SW corner were collected |
Completion
as observed on 14-Aug-12 |
14-Aug-12 |
120814_01 |
The
northern seawall has been removed to below high water mark, and muddy boom is
observed going into the Victoria Harbour while seawall blocks are being
removed. The contractor is
strongly recommended to provide rectification measures to avoid muddy boom
and violations to EP (TS1) |
Impermeable
barriers were deployed to cover sloping seawall |
Completions
as observed on 21-Aug-12 |
14-Aug-12 |
120814_02 |
Chemical
waste and wastewater should be cleared from drip trays (TS1) |
Chemical
waste and wastewater were removed. |
Completions
as observed on 21-Aug-12 |
14-Aug-12 |
120814_03 |
Oil leakage
should be cleared as chemical waste (TS4 and TPCWAE) |
Oil leakage
was cleared as chemical waste. |
Completions
as observed on 21-Aug-12 |
14-Aug-12 |
120814_04 |
Floating
refuse should be collected (Western side of TPCWAE (landing steps)) |
Floating
refuse was collected |
Completions
as observed on 21-Aug-12 |
14-Aug-12 |
120814_05 |
It has been
observed that the contractor has started to remove oil stains on water
surface, but some oil stains can still be observed, the contractor is
reminded to identify and treat at the source. |
Oil stains
were being removed as chemical waste. |
Completions
as observed on 21-Aug-12 |
21-Aug-12 |
120821_01 |
TS4 - Site
drainage system shall be cleaned regularly and properly maintained such that it
could be adequate to handle the runoff capacity. |
Drainage
channels were cleared of mud. |
Completion
as observed on 28-Aug-12 |
21-Aug-12 |
120821_02 |
TS4 - Site
drainage layout plan and measures shall be reviewed and updated to tally with
the discharge license requirement. |
Updated
drainage plan was provided that tally with the discharge license requirement. |
Completion
as observed on 28-Aug-12 |
21-Aug-12 |
120821_03 |
Impermeable
barrier were observed inadequate to protect the removed seawall location
requiring further trimming/dredging at TS1. |
More silt
curtains and impermeable barriers were provided at TS1. |
Completion
as observed on 28-Aug-12 |
21-Aug-12 |
120821_04 |
Inadequate
silt curtain were observed for protecting trimming work at breakwater at TS1. |
More silt
curtains and impermeable barriers were provided at TS1. |
Completion
as observed on 28-Aug-12 |
8.0.3.
Four site inspections for Contract no. HY/2009/18
was carried out during this reporting period. No observations was found in the
reporting month.
8.0.4.
Four site inspections for Contract no. HY/2009/19
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.2.
Table 8.2 Summary of Environmental
Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120823_01 |
23-Aug-12 |
Overflow into sea from drainage channel was observed at ferry
pier 2, the contractor is strongly recommended to provide adequate measures
to ensure the site drainage is adequate. |
Measures were provided to improve
site drainage. |
Completion as observed on 30-Aug-12 |
120823_02 |
23-Aug-12 |
Multiple oil stains were observed at Portion VII, the contractor
should removed the oil stains as chemical waste and identify and treat at
source. |
The oil stain was removed. |
Completion as observed on 30-Aug-12 |
8.0.5.
Four site inspections for Contract no. HK/2009/01
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.3.
Table 8.3 Summary of Environmental
Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120801_01 |
1-Aug-12 |
The condition of tree protection fences for trees (T608, 061)
should be improved (TST) |
The tree protection fences condition were improved. |
Completion as observed on 8-Aug-12 |
120801_02 |
1-Aug-12 |
The oil stain was observed on the ground which should be removed
and disposed as chemical waste. (VIP area, Water Channel) |
The oil stain was removed |
Completion as observed on 8-Aug-12 |
120808_01 |
8-Aug-12 |
Watering during breaking should be provided for dust suppression |
Watering was provided. |
Completion as observed on 16-Aug-12 |
120816_01 |
16-Aug-12 |
Drip tray should be provided for chemical containers (VIP area) |
Drip tray was provided. |
Completion as observed on 22-Aug-12 |
8.0.6.
Four site inspections for Contract no. HK/2009/02
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.4.
Table 8.4 Summary of Environmental
Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120802_01 |
2-Aug-12 |
The seepage of muddy water from the sheet pile was observed.
Better protection should be provided to prevent seepage and the silt curtain
should be deployed for protection. (Eastern sheet pile) |
Silt curtain was provided. |
Completion as observed
on 9-Aug-12 |
120815_01 |
15-Aug-12 |
The tarpaulin sheet should be provided for the transfer of
sediment to barge should be replaced. (WCR1) |
The tarpaulin sheet was provided. |
Completion as observed
on 22-Aug-12 |
120815_02 |
15-Aug-12 |
The condition of temporary drainage system should be improved to
ensure its efficiency. (Gate 2) |
The condition of temporary drainage system was improved. |
Completion as observed
on 22-Aug-12 |
120822_01 |
22-Aug-12 |
The stockpile should be covered by tarpaulin sheet (Next to
SPCA, Small ex-pet garden) |
The stockpile was removed. |
Completion as observed
on 30-Aug-12 |
120822_02 |
22-Aug-12 |
The maintenance of the U-channel should be improved and the sand
bags should be provided to prevent surface runoff. (small ex-pet garden) |
The condition of U-channel was improved. |
Completion as observed
on 30-Aug-12 |
8.0.7.
Four site inspections for Contract no. HY/2009/17
were carried out during this reporting period. No observation was found in the
reporting month.
8.0.8.
Four site inspections for Contract no. HK/2010/06
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.5.
Table 8.5 Summary
of Environmental Inspections for Contract no. HK/2010/06
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120730_01 |
30-Jul-12 |
The floating debris should be removed regularly. (2w) |
The floating debris should be cleaned regularly |
Completion
as observed on 7-August-12 |
120730_02 |
30-Jul-12 |
Chemical containers should be provided with drip tray or store
into the designated storage area (2w) |
Chemical containers were removed. |
Completion
as observed on 7-August-12 |
120807_01 |
7-Aug-12 |
Better protection should be provided at the edge of the platform
to prevent surface runoff (2w) |
The protection was provided |
Completion
as observed on 16-August-12 |
120807_02 |
7-Aug-12 |
The split was observed in U-channel which should be repaired
immediately (2e) |
The U-channel was repaired |
Completion
as observed on 16-August-12 |
120725_04 |
25-Jul-12 |
The oil
stain was observed on the ground which should be removed and disposed as
chemical waste (2w) |
The oil
stain was removed as chemical waste. |
Completion
as observed on 30-Jul-12 |
120816_01 |
16-Aug-12 |
The oil stain was observed on the platform which should be
removed and disposed as chemical waste (2w) |
The oil stain was removed as chemical waste. |
Completion
as observed on 20-August-12 |
120816_02 |
16-Aug-12 |
The condition and the silt accumulated in U-channel should be
improved and removed (2e) |
The condition of U-channel was improved. |
Completion
as observed on 20-August-12 |
120816_03 |
16-Aug-12 |
Drip tray should be provided for oil drums (2w) |
The oil drums were removed. |
Completion
as observed on 20-August-12 |
120820_01 |
20-Aug-12 |
The overflow of temporary sedimentation tank was observed. The
contractor should review the adequacy of the sedimentation tank and provide
the sand bags around the edge of the platform to prevent surface runoff (2w) |
The temporary sedimentation tank was removed. |
Completion as
observed on 27-August-12 |
120820_02 |
20-Aug-12 |
The filter for oil interceptor should be replaced (2w) |
The filter was replaced. |
Completion
as observed on 3-September-12 |
120827_01 |
27-Aug-12 |
The condition of U-channel should be improved (2w) |
The condition of U-channel was improved. |
Completion
as observed on 3-September-12 |
9.0.1.
No environmental complaint was received in the
reporting period.
9.0.2.
The
details of cumulative complaint log and updated summary of complaints are
presented in Appendix 9.1
9.0.3.
Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2
respectively.
Table 9.1 Cumulative Statistics on
Complaints
Reporting Period |
No. of Complaints |
Aug 12 |
0 |
Sep 10 to Jul 12 |
20 |
Total |
20 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2.
The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table 10.1 Summary of Key Construction Activities of
Individual Contract(s) to be commenced in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HY/2009/15 |
¡P
Diaphragm
wall construction works at TS4 ¡P
ELS
preparation works at TS4 ¡P
Rock
breaking works at TPCWAE ¡P
Tunnel
works at TS1 ¡P
Bored
piling at eastern breakwater ¡P
Horizontal
drilling along west portal of mined tunnel |
¡P
Watering
any dust generating activities ¡P
Checking
all drip trays frequently and clear any stagnant water and mud inside it. ¡P
Noise
control measures shall be provided during restricted hours. |
HY/2009/17 |
¡P
ELS
works for basement construction for pile cap construction. |
¡P
Noise
barrier shall be implemented; and ¡P
Watering
any dust generating activities |
HY/2009/18 |
¡P
Excavation
of trial pit ¡P
Transplanting
of trees ¡P
Hoarding
erection and modification ¡P
Installation
of couplers, UU detection, trial trench, pre-drilling ¡P
Site
investigation and pre-drill works ¡P
Excavation ¡P
Diaphragm
wall construction ¡P
Sheet
Piling ¡P
Drainage
works ¡P
Tunnel
works ¡P
Top
down slab construction ¡P
Trough
structure construction and associated drilling and grouting ¡P
Road
works ¡P
OHVD
installation ¡P
Pipe-piling
works ¡P
Cooling
main bridge construction ¡P
Bridge
A construction ¡P
Pre-bored
H-pile ¡P
Pumping
test |
¡P
Noise
barrier shall be implemented; and ¡P
Noise
level shall be controlled by reducing piling rate and no. of plants working
in parallel. ¡P
Dust
control during dust generating works ¡P
Provide
protection works to ensure no runoff out of site area or direct discharge
into public drainage system. ¡P
Appropriate
plants and measures should be taken to ensure adequate protections are
provided for trees being transplanted. |
HY2009/19 |
¡P
Road
works at Watson Road ¡P
Bored
piling (Land) ¡P
Ground
contamination assessment ¡P
Pre-drilling
works for bored pile and Diaphragm wall ¡P
D-wall
Construction (North & South Section) ¡P
Guide
wall construction for D-wall / Barette at North side ¡P
Construction
works for Box Culvert T ¡P
Marine
Piling ¡P
Construct
ion of socket-H pile ¡P
Construction
of pre-bored H-pile works for Culvert U ¡P
Construction
of 1500f drainage pipe ¡P
Construction
of Pile cap & column (Land) ¡P
Dismantling
of marine platform |
¡P
Noise
level shall be controlled by reducing the pilling operation rate. ¡P
Noise
barrier shall be implemented. ¡P
Dust
control during dust generating works ¡P
Provide
protection works and adequate drainage system to ensure no direct discharge
into public drainage system or the sea. |
HK2009/01 |
¡P
Preparation
works for pre-bored H-pile installation including excavation to +2mPD at
northern side between Ch120 and Ch190 ¡P
Backfilling
for the extent of exhaust duct section for pipe laying works for cross
harbour watermains ¡P
Construction
of SCL top slab (Bay 1 and Bay 2) ¡P
Remedial
works for SCL Diaphragm Wall ¡P
Installation
of dewatering system and equipment at SCL ¡P
Backfilling
works of the Area 3 to the required level for subsequent handover of site area |
¡P
Noise
level shall be controlled by reducing no. of plants working in parallel. ¡P
Well
maintained enclosures for grouting and bentonite mixing plants. ¡P
Provide
protection works and adequate drainage system to ensure no direct discharge
into public drainage system or the sea. ¡P
Dust
control during dust generating works |
HK/2009/02 |
¡P
Deep
excavation and strut installation works below -18mPD for western tunnel
portion and below -19mPD for eastern tunnel portion ¡P
Diaphragm
wall construction for Panel C107, P108, C109, C111, P112, C113, P114 and
C115 |
¡P
Well
maintain the enclosures for grouting and bentonite mixing plants. ¡P
Dust
control during dust generating works ¡P
Provide
protection works to ensure no runoff out of site area or direct discharge
into public drainage system. |
HK/2010/06 |
¡P
Construction
of Pre-cast Unit in China |
¡P
Air
pollution control during transportation |
10.0.3.
The construction works of Contract no. 04/HY/2006 ¡V
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A was completed, and the FEP was surrendered by the Contractor
on 11 February 2011.